Fichten solar park

ENERPARC AG's Fichten solar park is located in the Franconian Alb (Bavaria). The plant covers an area of 22.18 hectares and went into operation in December 2018 (first construction phase) and February 2020 (second construction phase). With a row spacing of 2.3 to 2.4 metres, the row spacing is relatively small. The paths are gravelled. The shape of the system adapts to the relief.

Tim Peschel
Operator

ENERPARC AG

Performance

20.1 MW

Size

22.2 ha

In operation since

2020

Federal state

Bavaria

Coordinates

49.2024736635 - 11.8141491183

Previous utilisation

Arable land

Table of contents

These species groups were analysed here:
Species groupsInvestigated
Plants
Locusts
Butterfly
Dragonflies
Reptiles
Amphibians
Birds
Bats
Miscellaneous
= Investigation conducted only for the study
= Investigation carried out on behalf of the operators

Natural environment and special features

Natural space

Franconian Alb

Surroundings

In addition to arable land, the site is bordered by some mixed woodland. A small area of forest is enclosed by the plant on its northern and eastern sides. The US military training area Hohenfels is located around two kilometres north of the Fichten solar park.

Relief

The site is located in the Franconian Alb at 460 to 490 metres above sea level in a small valley. The relief slopes down towards the centre of the site. There are elevations around the site.

Biotope

This is a former arable farmland. A row of trees and shrubs mapped as biotopes was excavated and relocated.

Floor

Soil type

Rendzina / brown earth rendzina / pararendzina from slope debris over limestone, marl and dolomite rocks alternating with shallow brown earth over terra fusca / terra fusca-parabrown earth from silty-clayey over-deposition products of limestone weathering

Soil type

Clay slurries

Construction method

GRZ

0.6

Row spacing

2.3m

Sunlit strip 

0.9m

Tilt angle Module tables

20°

Modules on top of each other

6 pieces

Description of the racks

The frame is secured to the ground by means of ram posts with cross struts.

Type of modules

Monofacial modules were installed.

Paths

Gravel paths were laid in the area.

Management

Mowing

The Fichten solar park is grazed. The plant is divided into sub-areas and each is subjected to impact grazing.

Sowing regional seeds 
No

Equalisation measures

Information on compensatory measures

The following compensatory measures were carried out in spruce trees:

  • Planting measures
  • Extensive grassland development through self-vegetation
  • An area equalisation of 4.6 hectares was implemented on the site of the solar park.

Details of the measures can be found in section 13.3 of the explanatory memorandum to the development plan, including the environmental report.